Bid Abstract

SAP 036-332-003 - CSAH 332 - Mill, Stabilized FDR, PaveKGM Contractors Inc. Hawkinson Construction Knife River Materials-Northern Minnesota Ulland Brothers, Inc. Mark Sand & Gravel Co. Northland Constructors of Duluth, LLC 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$28,000.00$28,000.00$129,000.00$129,000.00$82,000.00$82,000.00$93,131.20$93,131.20$85,000.00$85,000.00$41,000.00$41,000.00
2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT88$4.40$387.20$4.50$396.00$2.00$176.00$10.35$910.80$10.00$880.00$4.50$396.00
2112.501SUBGRADE PREPARATIONROAD STA43$469.50$20,188.50$730.00$31,390.00$1,500.00$64,500.00$270.00$11,610.00$1,200.00$51,600.00$2,000.00$86,000.00
2118.501AGGREGATE SURFACING CLASS 1TON500$16.00$8,000.00$13.15$6,575.00$1.00$500.00$27.00$13,500.00$10.00$5,000.00$24.00$12,000.00
2211.501AGGREGATE BASE CLASS 5TON3,955$13.40$52,997.00$13.15$52,008.25$16.00$63,280.00$26.60$105,203.00$15.70$62,093.50$19.50$77,122.50
2215.501FULL DEPTH RECLAMATION 8" DEPTHSQ. YD.15,306$1.25$19,132.50$1.20$18,367.20$2.15$32,907.90$1.15$17,601.90$1.90$29,081.40$1.10$16,836.60
2215.501FULL DEPTH RECLAMATION 11" DEPTHSquare Yard18,367$2.30$42,244.10$1.40$25,713.80$1.35$24,795.45$1.25$22,958.75$1.90$34,897.30$1.10$20,203.70
2215.604STABILIZED FULL DEPTH RECLAMATIONS Y18,367$7.00$128,569.00$6.45$118,467.15$7.00$128,569.00$7.35$134,997.45$7.20$132,242.40$7.00$128,569.00
2232.501MILL BITUMINOUS SURFACE (10.0")SQ YD18,367$2.90$53,264.30$4.63$85,039.21$4.00$73,468.00$3.45$63,366.15$4.50$82,651.50$4.00$73,468.00
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLONS3,902$2.40$9,364.80$3.00$11,706.00$0.01$39.02$2.50$9,755.00$2.50$9,755.00$2.50$9,755.00
2360.501TYPE SP 12.5 WEARING COURSE MIXTURE (3,C)TON9,028$51.40$464,039.20$48.60$438,760.80$54.75$494,283.00$57.00$514,596.00$58.00$523,624.00$95.00$857,660.00
2563.601TRAFFIC CONTROLLUMP SUM1$8,000.00$8,000.00$15,000.00$15,000.00$10,900.00$10,900.00$11,200.00$11,200.00$15,000.00$15,000.00$10,500.00$10,500.00
2563.602RAISED PAVEMENT MARKER TEMPORARYEACH35$3.50$122.50$2.00$70.00$8.00$280.00$1.15$40.25$20.00$700.00$1.15$40.25
2580.603INTERIM PAVEMENT MARKINGLIN FT415$1.90$788.50$2.00$830.00$2.50$1,037.50$1.50$622.50$2.00$830.00$2.40$996.00
 Totals for project SAP 036-332-003 $835,097.60 $933,323.41 $976,735.87 $999,493.00 $1,033,355.10 $1,334,547.05
 
Contract Total:$835,097.60$933,323.41$976,735.87$999,493.00$1,033,355.10$1,334,547.05