036-608-022 - CSAH 8 Culvert Replacement Double 16' x 12' Box CulvertsWagner Construction Inc. Gladen Construction Inc. Ulland Bros Hoover Construction Co. KGM Contractors Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$13,650.00$13,650.00$21,500.00$21,500.00$32,858.86$32,858.86$40,000.00$40,000.00$58,000.00$58,000.00
2101.511CLEARING AND GRUBBINGLUMP SUM1$4,682.00$4,682.00$3,000.00$3,000.00$5,000.00$5,000.00$2,100.00$2,100.00$2,500.00$2,500.00
2104.501REMOVE PIPE CULVERTSLIN FT94$50.00$4,700.00$385.00$36,190.00$100.00$9,400.00$170.00$15,980.00$25.00$2,350.00
2104.513SAWING BITUMINOUS PAVEMENTLIN FT48$8.25$396.00$5.00$240.00$10.00$480.00$11.00$528.00$5.00$240.00
2105.501COMMON EXCAVATIONCU YD4,830$5.00$24,150.00$6.25$30,187.50$9.00$43,470.00$7.70$37,191.00$16.00$77,280.00
2105.604GEOTEXTILE FABRIC TYPE VISQ YD2,313$2.00$4,626.00$1.95$4,510.35$2.00$4,626.00$3.00$6,939.00$4.00$9,252.00
2118.501AGGREGATE SURFACING CLASS 5TON390$19.50$7,605.00$30.75$11,992.50$23.00$8,970.00$23.00$8,970.00$25.00$9,750.00
2211.501AGGREGATE BASE CLASS 5TON1,997$18.50$36,944.50$28.75$57,413.75$20.00$39,940.00$23.00$45,931.00$20.00$39,940.00
2412.51116X12 PRECAST CONCRETE BOX CULVERTLIN FT176$1,489.00$262,064.00$1,415.00$249,040.00$1,500.00$264,000.00$1,800.00$316,800.00$1,800.00$316,800.00
2412.51216X12 PRECAST CONCRETE BOX CULV END SECTEACH4$22,436.00$89,744.00$18,580.00$74,320.00$21,000.00$84,000.00$22,600.00$90,400.00$25,000.00$100,000.00
2451.503GRANULAR BACKFILL (CV)CU YD4,093$22.00$90,046.00$18.80$76,948.40$18.00$73,674.00$24.00$98,232.00$22.00$90,046.00
2451.509AGGREGATE BEDDING (CV)CU YD620$31.00$19,220.00$54.00$33,480.00$60.00$37,200.00$40.00$24,800.00$43.00$26,660.00
2511.501RANDOM RIPRAP CLASS IIICU YD150$113.00$16,950.00$46.00$6,900.00$65.00$9,750.00$60.00$9,000.00$75.00$11,250.00
2563.601TRAFFIC CONTROLLUMP SUM1$2,162.00$2,162.00$4,500.00$4,500.00$3,200.00$3,200.00$3,900.00$3,900.00$4,700.00$4,700.00
2573.502SILT FENCE, TYPE MSLIN FT1,303$3.00$3,909.00$3.00$3,909.00$2.80$3,648.40$5.00$6,515.00$1.85$2,410.55
2573.505FLOTATION SILT CURTAIN TYPE MOVING WATERLIN FT106$23.00$2,438.00$22.00$2,332.00$22.00$2,332.00$38.50$4,081.00$20.00$2,120.00
2573.540FILTER LOG TYPE STRAW BIOROLLLIN FT500$5.00$2,500.00$5.00$2,500.00$4.85$2,425.00$4.25$2,125.00$3.15$1,575.00
2575.523EROSION CONTROL BLANKETS CATEGORY 3NS Y496$2.00$992.00$1.75$868.00$1.69$838.24$2.50$1,240.00$4.45$2,207.20
2575.555TURF ESTABLISHMENTLUMP SUM1$9,282.00$9,282.00$2,500.00$2,500.00$2,475.00$2,475.00$7,700.00$7,700.00$8,500.00$8,500.00
2575.571RAPID STABILIZATION METHOD 3MGAL5.5$716.00$3,938.00$700.00$3,850.00$675.00$3,712.50$1,320.00$7,260.00$250.00$1,375.00
 Totals for project 036-608-022 $599,998.50 $626,181.50 $632,000.00 $729,692.00 $766,955.75
 
Contract Total:$599,998.50$626,181.50$632,000.00$729,692.00$766,955.75